On October 28, 2026, GE Vernova announced an agreement to acquire Trench Group, a Berlin-based maker of high-voltage grid equipment, from investment firm Triton Partners for $9.0 billion. The price is equal to 13 times the earnings (adjusted EBITDA) Trench Group (Trench) expects to make in 2028. The deal is expected to close in late 2027, subject to regulatory approval.

Trench manufactures bushings – insulated connectors that carry high-voltage current safely into and out of transformers – as well as instrument transformers and coils. It sells to more than 800 utilities and hyperscalers, amounting to approximately $5 billion in orders. As such, GE Vernova is presenting the deal as an industrial move, rather than a digital one. Trench is already one of the organization’s suppliers, and bringing it in-house gives GE Vernova more control over key components and supply chain issues that can slow grid expansion initiatives. It also brings added capacity, with a new Trench plant in Charlotte, North Carolina due to start producing 765kV bushings in late 2027. For Trench, this is the second change of owner in under four years: Triton Partners completed its carve-out from Siemens Energy in April 2024.

Buying a bottleneck, not a technology

Verdantix sees the deal as a bet on equipment shortages rather than on new technology. Bushings make up only 5-8% of the cost of a transformer, according to GE Vernova CEO Scott Strazik, but a transformer cannot be delivered without them – and customers often insist on a specific manufacturer’s bushings. GE Vernova currently buys most of its bushings externally. Buying Trench will give it ownership of a supplier that some of its competitors also rely on.

The deal fits a wider pattern. In February 2026, GE Vernova paid $5.3 billion for the remaining 50% share in transformer maker Prolec GE. In the same quarter, it sold its Proficy manufacturing software business to TPG. GE Vernova is putting its money into physical grid equipment, the area of the market in which demand most outstrips supply.

For providers of digital grid technologies, Verdantix sees three implications:

  • Equipment shortages increase the value of software that gets more out of existing assets. If a new transformer can take years to arrive, utilities need the equipment they already own to last longer and carry more power. That boosts demand for software that monitors equipment condition, predicts failures, and helps decide what to repair, replace or run harder. Examples include online monitoring of transformers and bushings, and dynamic line rating – which calculates how much power a line can safely carry in current weather. Vendors that can show, in financial terms, the asset life they add or the spending they avoid will find willing buyers.
  • Equipment makers will use scarce delivery slots to sell their own software. Scott Strazik noted that the Trench deal will let GE Vernova offer “better integrated solutions”. A manufacturer that controls the whole equipment package can offer hardware, protection, control, monitoring and software together – and customers keen to secure a delivery date may accept the full bundle. This makes it harder for independent software vendors to compete. Utilities should avoid being locked into one supplier’s software as the price of getting equipment and require open, standards-based data access, such as IEC 61850.
  • Equipment availability will shape when new customers can connect. Grid planning tools usually assume equipment can be bought when needed – at a price. With waits of several years, and a key supplier now owned by one manufacturer, availability itself is becoming a limit on how quickly utilities can connect data centres and other large customers. Planning software that factors in supplier capacity and delivery risk will help utilities give customers reliable connection dates.

What to watch

Before the deal closes in late 2027, Verdantix will be watching two things. First, whether GE Vernova’s competitors follow its steps and turn to other bushing suppliers or build their own capacity. Second, whether GE Vernova starts selling Trench components together with its own monitoring and grid software.

Utilities should treat transformer and bushing health data as a core input to investment planning, not just a maintenance task, and check how their supply agreements could be affected if Trench’s priorities change. Digital grid vendors should focus on the problem this deal highlights – not enough equipment, arriving too slowly – and show how their software extends asset life, frees up network capacity and connects customers sooner.